QA interview question
Metrics & estimationMiddleOccasionalTheory

How do Wideband Delphi and Planning Poker differ as collaborative estimation techniques, and does Scrum require either of them?

Answer

Wideband Delphi runs anonymous, independent estimates in rounds, with a facilitator sharing the spread and reasoning between rounds until estimates converge, which reduces anchoring and dominant-voice bias. Planning Poker is a lighter-weight, faster variant using cards to force simultaneous reveal and quick discussion of outliers, usually for near-term backlog items rather than large deliverables. Neither is mandated by Scrum; the Scrum Guide does not require story points or Planning Poker, and teams can use them, another sizing method, or none at all.

Strong answer includes

  • describes Wideband Delphi's multi-round anonymous convergence process
  • describes Planning Poker as a lighter, faster simultaneous-reveal variant
  • explicitly states Scrum does not require either technique

Practical example

A new Scrum Master insisted the team 'must' use Planning Poker because 'Scrum requires it.' The team lead pointed to the Scrum Guide showing no such requirement, and the team switched to a lighter T-shirt-sizing pass for small items, reserving a Wideband Delphi-style multi-round estimate only for a handful of genuinely uncertain, high-effort items.

#estimation#planning-poker#wideband-delphi