Search GimmeJob

Type at least 2 characters. Enter also searches by meaning.
QA interview question
Metrics & estimationMiddleOccasionalPractical

How would you use three-point estimation for a risky testing task?

Answer

Estimate an optimistic effort if the favorable assumptions hold, a most-likely effort for the expected path, and a pessimistic effort for credible complications. Discuss what creates the spread, such as unstable environments, unfamiliar technology, data preparation, defect investigation or dependency delays. A common PERT-style estimate is (optimistic + 4 × most likely + pessimistic) ÷ 6, but the inputs and uncertainty matter more than the formula. Report the range, assumptions and confidence, separate external waiting time, and re-estimate when the identified risks resolve or occur.

Strong answer includes

  • defines optimistic, most-likely and pessimistic cases
  • ties the estimate range to explicit uncertainty drivers
  • uses the calculation as decision support rather than a guarantee

Practical example

For testing a third-party payment gateway integration, a tester estimates 3 days optimistic (if the sandbox works first try), 6 days most likely, and 15 days pessimistic (if the sandbox is flaky and support response is slow, which happened on the last integration). The PERT calculation gives about 7 days, which the tester reports alongside the explicit risk driver — sandbox reliability — so the project manager can decide whether to pad the schedule or push vendor support to prioritize a stable test environment.

#three-point-estimation#pert#uncertainty#test-estimation

Sources

ISTQB CTFL syllabus v4.0.1ISTQB · Testing vocabulary, principles, lifecycle and test-design concepts