How do you estimate testing when scope and uncertainty are both changing?
Answer
Decompose work, use analogous evidence and team estimates, include setup, investigation and retest, and express a range with assumptions and risk. Re-estimate when evidence changes instead of defending an early single number.
Strong answer includes
- decomposition and historical evidence
- range and assumptions
- continuous re-estimation
Practical example
For a feature with unclear scope, a QA lead estimated testing as a range of 3-5 days based on similar past features, explicitly noting the assumption of stable test data; when scope grew mid-sprint, the estimate was revised to 6-8 days rather than silently absorbed.