Are STLC activities sequential, and how do they work in Agile or continuous delivery?
Answer
No. Test activities have logical relationships, but they overlap, repeat and feed back into one another. In Agile, analysis and design can begin during refinement, implementation can happen alongside development, execution can run continuously in CI, monitoring and control can change priorities at any time, and completion is evaluated per story, sprint, release or change depending on context. The same activities still exist; the cadence and granularity change.
Strong answer includes
- rejects a rigid waterfall interpretation
- shows where activities occur in refinement, development, CI and release work
- explains that Agile changes cadence rather than eliminating test activities
Practical example
For a small API story, QA can review acceptance criteria on Monday, design cases while the endpoint is being coded, prepare test data the same day, run contract and integration tests on every pull request, adjust regression scope after a defect is found, and close the testing objective when the agreed evidence is complete.