How do product risks differ from project risks in a test strategy?
Answer
Product risks concern undesirable quality outcomes such as incorrect behaviour, security or performance; project risks threaten delivery, such as skills, environments or schedule. Tests mitigate product risk, while planning and management actions address both kinds.
Strong answer includes
- quality outcome versus delivery threat
- different mitigations
- links risks to actions
Practical example
On a project where the payment gateway integration kept slipping (a project risk from vendor delays), the team ran extra exploratory testing on the checkout flow itself (mitigating the product risk of incorrect charge amounts) while separately escalating the vendor delay to management.