Search GimmeJob

Type at least 2 characters. Enter also searches by meaning.
QA interview question
Metrics & estimationMiddleOccasionalTheory

How do lead time, cycle time, throughput and WIP relate to each other?

Answer

Lead time runs from when work is requested to when it is delivered; cycle time runs from when work actively starts to when it finishes, a narrower window inside lead time. Throughput is how many items finish per period, and WIP, work in progress, is how many items are in flight at once. Little's Law ties them together: average cycle time is roughly average WIP divided by average throughput, so cutting WIP is often a more reliable way to shorten cycle time than asking people to work faster.

Strong answer includes

  • distinguishes lead time's request-to-delivery span from cycle time's active-work span
  • defines throughput and WIP precisely
  • connects the four through the WIP-to-throughput relationship rather than treating them as unrelated numbers

Practical example

A team with rising cycle time assumed testers needed to work faster; plotting WIP alongside cycle time showed WIP had tripled because every engineer was context-switching across parallel stories. Capping WIP per person, not adding pressure, brought cycle time back down within two sprints.

#flow-metrics#cycle-time#throughput

Sources

DORA research programGoogle Cloud · Software delivery performance (current five-metric model) and organizational capabilitiesThe Scrum GuideScrum Guides · Scrum accountabilities, events, commitments and empiricism